All GBCSA projects include a Round 1 and a Round 2 assessment. Part of the elapsed time is fixed by GBCSA and part depends on the project team.
GBCSA lists four elements: the time to compile the Round 1 submission, GBCSA's Round 1 assessment, the project's response to the Round 1 comment and GBCSA's Round 2 assessment, which ends with a certification ruling.
| Certification system | Round 1 assessment | Round 2 assessment |
|---|---|---|
| Green Star | 7 weeks | 5 weeks |
| Net Zero | 4 weeks | 3 weeks |
| EWP | 4 weeks | 3 weeks |
| EDGE | 4 weeks | 3 weeks |
The durations cover GBCSA's processing time only. They exclude the time to compile the submission and to respond to Round 1 comments, which vary with the tool, the targets and the quality of the submission. Certification often follows the development timeline of the project or fit-out.
The figures are from GBCSA's certification process page read in November 2026 and may change. Check that page before planning.