Assessment rounds and timing

All GBCSA projects include a Round 1 and a Round 2 assessment. Part of the elapsed time is fixed by GBCSA and part depends on the project team.

What determines duration

GBCSA lists four elements: the time to compile the Round 1 submission, GBCSA's Round 1 assessment, the project's response to the Round 1 comment and GBCSA's Round 2 assessment, which ends with a certification ruling.

Fixed assessment durations

Certification systemRound 1 assessmentRound 2 assessment
Green Star7 weeks5 weeks
Net Zero4 weeks3 weeks
EWP4 weeks3 weeks
EDGE4 weeks3 weeks

What the durations leave out

The durations cover GBCSA's processing time only. They exclude the time to compile the submission and to respond to Round 1 comments, which vary with the tool, the targets and the quality of the submission. Certification often follows the development timeline of the project or fit-out.

Source

The figures are from GBCSA's certification process page read in November 2026 and may change. Check that page before planning.

The Green Building Council South Africa, the International WELL Building Institute and the other bodies named are cited for reference only. This resource is not affiliated with any of them.